[APBeta] Problems setting date and time (APv2b39)
Paul Rodman
paul at ilanga.com
Fri May 29 13:18:51 PDT 2009
On May 29, 2009, at 12:23 PM, Bruce Pipes wrote:
> Paul,
>
> I thought I had reported this problem, but I cannot find it in the
> APBeta archives. Screwy things happen when I try to set the date and
> time in a plan. I think the simplest way to see it is to do the
> following:
>
> Open a plan and click on the "day" in the Date/Time box.
>
> The first odd thing is the "month" gets highlighted.
>
> Click on the "day" again and it will be highlighted.
>
> Change the day and let the plan recalculate.
>
> The "day" will still highlighted, but when you try to change the day
> again, the highlighting jumps back to "month" and the month changes.
>
> Similar things happen when you try to change the time.
>
> Hope this is clear.
This has been logged, by more than one person. I will be attending to
it soon.
Which reminds me...
Paul R.